About the project
The Willoughby Farms Subdivision - Section 1 Rehabilitation Project consists of removal of the existing asphalt roadway pavement, stabilization of the underlying base, new asphalt pavement installation; bike path installation adjacent to the park, miscellaneous removal and replacement of curb and gutter, sidewalk, driveway aprons, and ADA crosswalk updates; drainage improvements; and landscape restoration.
We want to thank you for your patience and understanding as we continue with improvements to your street(s). We are getting closer to completing the pavement portion of construction. We know there have been temporary inconveniences, but we are happy with the progress made so far, and we will continue to try to minimize the inconvenience as best as we can. |
Project ScheduleStage I: April 1 - July 5; Stonegate Rd, Waverly Ln, Cloverdale Ln, Peach Tree Ln (west), and the following Courts: Dellwood, Peach Tree, Cloverdale, Driftwood, Arbordale, Cedar Grove, Waverly & Stonegate Stage II: July 1 - October 4; Wynnfield Dr, Haverford Dr, White Oak Dr, Peach Tree Ln (east), Dorchester Ave, Fernwood Ln, and the following Courts: Fernwood, White Oak, Ashcroft, and Dorchester |
September 6th Update
Progress continues! On Monday, September 9th, 2024 the contractor will begin paving the final asphalt surface throughout the entire subdivision. In advance of the paving operation, the contractor will be applying a tack-less prim coat, which provides a bond between the binder and surface lifts.
The contractor has proposed the paving schedule below (weather permitting):
The contractor has proposed the paving schedule below (weather permitting):
Monday, September 9th
- Peach Tree Court
- Dellwood Court
- Driftwood Court
- Arbordale Court
- Cedar Grove Court
- Stonegate Court
- Waverly Court
- Waverly Lane (Stonegate Road to Stonegate Road)
Tuesday, September 10th
- Cloverdale Lane (Stonegate Road to Haverford Drive)
- Arbordale Lane (Cloverdale Lane to Arbordale Court)
- Dorchester Avenue (Wynnfield Drive to Wynnfield Drive)
- Dorchester Court
- Ashcroft Court
Wednesday, September 11th
- Dorchester Avenue (Haverford Drive to Wynnfield Drive)
- Peach Tree Lane (Haverford Drive to Stonegate Road)
- White Oak Drive (Haverford Drive to Stonegate Road)
- White Oak Court
Thursday, September 12th
- Stonegate Road
- Peach Tree Lane (Stonegate Road to Stonegate Road)
Saturday, September 14th/Monday, September 16th
- Haverford Drive (Wynnfield Drive to Sleepy Hollow Road)
- Fernwood Lane (Wynnfield Drive to Haverford Drive)
Monday, September 16th/Tuesday September 17th
- Wynnfield Drive (Stonegate Road to Sleepy Hollow Road)
- Waverly Lane (Stonegate Road to Cloverdale Lane)
- Wynnfield Court
- Cloverdale Court
Additional Project Information
All of this work is weather/conditions permitting. All emergency Service Departments (Fire, Paramedics, Police will be notified of this work and will have access throughout the duration of the operations. All inquiries and concerns should be addressed to Razvan Calin, either through email at rcalin@cbbel.com or by calling 847-533-3013. Residents are also encouraged to download and utilize the "Algonquin Fix It " (aka See Click Fix) phone application and to get connected to the Village via our website and social media feeds on Facebook, Twitter and Instagram.
|
Thank you in advance for your cooperation during this important public improvement. With your patience and understanding, the Village will efficiently and effectively manage this project and provide a valuable new asset to your neighborhood. Respectfully submitted, Clifton V. Ganek, P.E. Village Engineer |